Scheduled (published schedule data), not measured outages.

All cities

FESCO · city view

Faisalabad

In FY 2024-25, FESCO reported 0.02 hours of load shedding a day to NEPRA: 8 of 10 companies (1 = most).

hours a day reported, FY 2024-25
0.02
rank of 10 companies, FY 2024-25 (1 = most)
8
highest year: FY 2012-13
7.8
years on record
13

These are the figures each company reported to NEPRA, not measurements. NEPRA says some companies under-report.

Year by year

Hours a day each company reported to NEPRA, by fiscal year (July to June). Faisalabad is the blue line, the dark grey line is the median of all companies and the light lines are the other companies.

02468101212-1314-1516-1718-1920-2122-2324-250.02

Faisalabad Median of all companies Other companies

Show the numbers
Fiscal yearFaisalabad, hours a dayMedian, hours a dayRank
2012-137.85.23 / 10
2013-147.254.2753 / 10
2014-154.333.71 / 10
2015-163.53.0152 / 10
2016-173.233.246 / 10
2017-180.742.68810 / 10
2018-190.321.69810 / 10
2019-2002.539 / 10
2020-2101.8710 / 10
2021-2212.47 / 10
2022-230.561.9159 / 10
2023-2402.410 / 10
2024-250.021.38 / 10

Share of the day

One ring per fiscal year, oldest inside. Each arc is the part of a 24-hour day that FESCO reported as load shedding, starting at midnight at the top.

Roshni has no published load-shedding schedule for FESCO, so only the figures it reported to NEPRA are shown.